10/31/18 – Construction Update

We made a lot of progress on the new campus this past month. Check out the list of fun stats below:

  • Safety trained over 300 onsite trade partners! Safety first, always!
  • Received Over 400 Deliveries
  • Installed Over 1,200 LF of Storm Drain
  • Installed Over 3,700 LF of Sewer Pipe
  • Poured Over 1,200 CY of Concrete for Footings
  • Pumped over 325 Yards of Grout
  • Installed Over 50,000 Blocks on 7 Buildings
  • Administration Building Stems Complete!
  • Special Education Classroom Building Stems Complete!
  • Classroom Building at 16’-0” AFF (Above Finish Floor)
  • Cafeteria at 12’-0” AFF
  • Innovation Center at 20’-0” AFF
  • Science Classrooms at 8’-0” AFF
  • Gymnasium Stems Complete!

We’re looking forward to November as steel has started showing up onsite!